Concrete Estimate Template for Slabs, Driveways and Patios
Square feet and thickness, cubic yards delivered, rebar or mesh, base gravel, finish type, and pump or short-load fees on one PDF.
- Free, no signup
- PDF in about two minutes
- Works on a phone
Concrete is bought by the yard and sold by the foot
Your biggest cost arrives by the cubic yard, but the homeowner thinks in square feet. A concrete estimate has to connect the two: area, thickness, the yards that come out of it, and everything that happens before and after the truck shows up. Most of the labor is in prep and finish, not the pour itself, and most of the surprises are in the ground. Write the estimate so both are visible.
Line items: prep, reinforcement, pour, finish, fees
Give each stage its own row. Clients compare concrete bids line by line, and a lower bid usually skipped the base or the steel.
| Description | Quantity | Unit | Unit price |
|---|---|---|---|
| Excavate and grade for 4 in. base | 300 | sq ft | $1.50 |
| Gravel base, 4 in., compacted | 300 | sq ft | $1.75 |
| Wire mesh, 6x6 W1.4 | 300 | sq ft | $0.60 |
| Stamped finish, ashlar slate pattern, 1 color | 300 | sq ft | $9.00 |
| Exposed aggregate finish | 150 | sq ft | $5.50 |
| Pump truck, line pump, minimum | 1 | each | $850 |
Rebar or mesh, forms, and the finish type are where bids differ most. Name them. "Concrete patio, $4,800" tells the client nothing they can compare.
Worked example: 20 x 20 driveway replacement, 4 in.
The old driveway is cracked and heaved. Tear it out, rebuild the base, pour a new 4 in. slab with rebar and a broom finish. The garage side needs no form.
Volume: 400 sq ft x 4 in. / 12 / 27 = 4.94 cubic yards. Order 5.5 yards.
| Description | Qty | Unit | Unit price | Amount |
|---|---|---|---|---|
| Demo and haul existing slab, 4 in. | 400 | sq ft | $3.50 | $1,400.00 |
| Grade and compact 4 in. gravel base | 400 | sq ft | $1.75 | $700.00 |
| Forms, three sides | 60 | linear ft | $3.00 | $180.00 |
| #3 rebar, 18 in. on center, with chairs | 400 | sq ft | $1.25 | $500.00 |
| Ready-mix, 4,000 psi, delivered | 5.5 | cu yd | $185 | $1,017.50 |
| Place, broom finish, tool control joints | 400 | sq ft | $4.25 | $1,700.00 |
| Short-load fee (under 8-yard minimum) | 1 | each | $250 | $250.00 |
| Penetrating sealer, 1 coat | 400 | sq ft | $0.75 | $300.00 |
Subtotal: $6,047.50, about $15.12 per square foot including tear-out.
If the city requires a permit for the driveway apron or curb cut, add it as its own line and say who pulls it.
Free download
Concrete estimate template, ready to edit
The worked example above as a file, with its line items and terms already filled in. Change the prices, add your details and send it.
Or skip the file: fill it in above and download a PDFAll trade templates
Terms that belong on a concrete estimate
- Validity: 14 to 30 days. Ready-mix and fuel surcharges change often.
- Deposit: enough to cover the ready-mix order and base material, with the balance due when the pour is finished. Check your state's deposit rules.
- Weather: no pour in rain or when temperatures are forecast below 40°F without cold-weather measures. The date moves; the price does not.
- Cure: foot traffic after 24 to 48 hours, cars after 7 days. The client keeps vehicles off it, and you are not responsible for damage caused by use before then.
- Subgrade: unsuitable soil, buried debris, tree roots or old footings found during excavation are extra, priced per cubic yard removed.
- Utilities: you call 811 before digging; the owner marks private lines such as sprinklers and low-voltage lighting.
- Exclusions: landscaping repair past 2 ft from the forms, sprinkler line repair, permits unless listed.
The common dispute: cracks
Within a year, nearly every slab has a crack somewhere, and nearly every homeowner calls about it. Control joints direct where it happens, but they do not stop it. Settle the expectation on paper before the pour:
"Concrete shrinks as it cures. Control joints are cut to direct cracking. Hairline cracks under 1/8 in. wide with no vertical displacement are normal and are not a defect. Cracks wider than 1/8 in. or with more than 1/8 in. of height difference within one year of the pour will be evaluated and repaired at our cost."
That sentence turns a vague complaint into a measurement. Bring a ruler and a coin to the callback, and photograph the slab on finish day so you have a record of how it left your hands.
Prices on this page are ballpark US figures in US dollars for early 2026. They show how a quote is put together, not a rate survey: price from your own costs and your local market.
How to use
Three things, then download
Your business name, the client and the line items are all a PDF needs. Tax, dates and terms are there when you want them.
- 01
Header with access notes
Business name, license number, job address, and a note on truck access: whether a mixer can reach the pour or a pump or buggies are needed.
- 02
Measure each pour
List every slab separately with square feet and thickness, then convert to cubic yards and add 5% to 10% for overage and subgrade variation.
- 03
Price prep, pour and finish
Demo, grading and base gravel, forms and reinforcement, then placement and finish per square foot, with pump and short-load fees on their own rows.
- 04
Lock the terms
Validity window, deposit, weather and cure rules, soft-subgrade clause and cracking language in the terms box. Download the PDF.
Use cases
Frequently asked questions
A plain 4 in. broom-finished slab typically runs $8 to $14 per square foot installed in most US markets. Stamped or colored concrete runs about $14 to $25, and tear-out of an old slab adds roughly $2 to $5 per square foot.
Multiply square feet by thickness in inches, divide by 12, then divide by 27. A 400 sq ft slab at 4 in. is about 4.9 cubic yards, so you would order 5.5 yards. Ready-mix commonly runs $150 to $200 per yard delivered.
Ready-mix plants charge extra when an order is under their truck minimum, which is often 6 to 10 yards. The fee is usually a flat charge or a per-yard charge for each yard short, so put it on its own line on small patio and sidewalk jobs.
When the mixer cannot get within chute reach of the forms, usually about 15 to 20 ft, or the pour is in a back yard. A line pump for a residential pour commonly costs $600 to $1,200 as a minimum charge, more for a boom pump.
Four inches is standard for passenger cars. Use 5 to 6 in. for heavy trucks, RVs, or the apron where delivery and garbage trucks turn. Going from 4 to 6 in. adds 50% more concrete, so price it as a separate option.
Concrete shrinks as it cures, and some cracking is normal. Control joints spaced at 2 to 3 times the slab thickness in feet, such as 8 to 12 ft on a 4 in. slab, give it a place to crack. State that hairline shrinkage cracks are not a defect.