Remodeling Estimate Template for Kitchens and Baths

Demo, rough-in, cabinets by the linear foot, countertops by the square foot, finish allowances and contingency on one PDF the homeowner can sign.

  • Free, no signup
  • PDF in about two minutes
  • Works on a phone

A remodel estimate prices what is behind the wall

New construction starts from a set of drawings. A remodel starts from a room someone lives in, with forty years of other people's decisions behind the drywall. The homeowner also lives with the mess, so they read the estimate closely: what comes out, what goes in, what they still have to choose, and what happens if the subfloor is soft. A remodeling estimate has to answer all four, and it has to do it in the units the trades actually price in.

Line items by phase, priced in trade units

Order the rows the way the job runs, and price each row in the unit the trade uses. Lump sums hide the parts the client will ask about.

DescriptionQuantityUnitUnit price
Bath demo: tub, tile, vanity, haul-off1job$1,600
Move shower valve and drain1each$850
Cement board and waterproofing membrane96sq ft$7
Porcelain wall tile, installed96sq ft$22
Vanity install, 36 in.1each$375
Vanity and faucet allowance1allowance$1,200

The same logic holds in a kitchen. Cabinets go by the linear foot of run because that is how the cabinet shop quotes you. Counters go by the square foot because the fabricator bills from the template. Circuits and fixtures go per each because the electrician and plumber price them that way. When the client asks why the number moved, you can point to one row.

Worked example: 10 x 12 kitchen, mid-range

Same layout, sink moves 4 ft to an island-facing wall, new cabinets and quartz, appliances supplied by the owner.

DescriptionQtyUnitUnit priceAmount
Demo: cabinets, counters, sheet vinyl, haul-off1job$2,400$2,400
Rough plumbing: move sink 4 ft, new DW supply1job$1,850$1,850
New 20A kitchen circuits4each$375$1,500
Semi-custom cabinets, installed24linear ft$450$10,800
Quartz countertop, installed, 1 sink cutout52sq ft$85$4,420
Backsplash tile, installed30sq ft$28$840
Fixture allowance: sink, faucet, lighting1allowance$2,000$2,000
Building permit and inspections1each$650$650

Estimate total: $24,460. A separate 10% contingency of $2,446 is billed only against approved change orders.

Flooring, drywall patching outside the backsplash area and appliance purchase are excluded and listed in the terms. If the client wants new flooring, that is a separate line, not a surprise in week three.

Free download

Remodeling estimate template, ready to edit

The worked example above as a file, with its line items and terms already filled in. Change the prices, add your details and send it.

Or skip the file: fill it in above and download a PDFAll trade templates

Allowances and contingency are different things

An allowance is a budget for something the client still has to choose: "Fixture allowance, $2,000. Selections above are billed at cost plus 15%; selections below are credited." A contingency covers what nobody can see yet: rot under the sink base, ungrounded wiring, a joist cut by the last plumber. Keep them on separate lines. Clients accept a contingency when it has a percentage, a clear trigger and a promise that unused money is not billed.

Terms for a remodel

  • Validity: 30 days. Cabinet and quartz pricing is re-confirmed after that.
  • Deposit and draws: deposit on signing to order cabinets, then draws at rough-in inspection, cabinet install, and completion. Check your state's deposit cap; California limits it to 10% or $1,000, whichever is less.
  • Lead times: semi-custom cabinets often take 6 to 10 weeks. Say the start date depends on delivery.
  • Exclusions: appliances, flooring outside the work area, painting other rooms, hazardous material abatement, structural changes not shown.
  • Change orders: any change to scope or price is written, signed and priced before the work is done.
  • Living conditions: state whether the kitchen will be out of service and for roughly how many weeks.

The common dispute: concealed conditions

The fight in remodeling is almost always about what turned up after demo. The client signed a number; you opened the wall and found a cracked drain or aluminum branch wiring. Without a clause, every extra dollar looks like a bait and switch. Put this in every remodeling estimate:

"This estimate covers visible conditions only. Concealed conditions found after demolition, including rot, water damage, mold, outdated wiring or plumbing, and framing defects, are not included. We will stop, show you the condition, and provide a written change order for approval before continuing."

Then photograph the condition the day you find it and attach the photo to the change order. The client sees the problem before they see the price.

Prices on this page are ballpark US figures in US dollars for early 2026. They show how a quote is put together, not a rate survey: price from your own costs and your local market.

How to use

Three things, then download

Your business name, the client and the line items are all a PDF needs. Tax, dates and terms are there when you want them.

  1. 01

    Header with license and rooms

    Business name, license number, the homeowner's name and job address, and a one-line scope naming the rooms being remodeled.

  2. 02

    Phase the remodel

    Line items grouped as demo, rough-in, cabinets and counters, tile and finish, then permits and fees, with materials and labor split where it matters.

  3. 03

    Price in trade units

    Cabinets per linear foot, countertops and tile per square foot, circuits and fixtures per each, and allowances for finishes the client has not picked.

  4. 04

    Lock contingency and changes

    State the contingency percentage, deposit and draw schedule, validity window and the written change-order rule in the terms box. Download the PDF.

Use cases

Kitchen remodels

Cabinets per linear foot, quartz or granite per square foot, backsplash tile per square foot, new circuits and appliance hookups per each.

Bathroom remodels

Tub-to-shower conversions, wall and floor tile per square foot, valve and drain relocation per each, vanity and fixtures as allowances.

Basement finishing

Framing per linear foot of wall, drywall per square foot, egress window per each, flooring per square foot and electrical per circuit.

Whole-house refresh

Paint per square foot of wall, flooring per square foot, trim per linear foot and fixture swaps per each, phased room by room.

Aging-in-place upgrades

Grab bars and comfort-height toilets per each, curbless showers per square foot, doorway widening per opening.

Frequently asked questions